District Construction Update


Posted Date: 05/04/2017

Thumbnail Image for Article 10188

Charlie Price of Compass Builders, the school’s contract engineering firm, reported that most of the projects from the 2013 and 2016 bond elections are completed or nearly completed. The life skills building is proceeding and the Big Green restrooms are near completion.

The only outstanding exceptions are the four largest projects: the auditorium upgrade, the stadium upgrade, upgrade of the floors in the elementary school and the new competition gymnasium.

The auditorium will begin renovation the day after graduation. The bleachers upgrade is complete with construction beginning on the new home concession stand and restrooms. 

The upgrade of the floors in the elementary school will begin in the facility as soon as classes are dismissed for the summer. Ground work is taking place at the new gym. 

Updates are presented at monthly board meetings at Central Office.

District Calendar

Upcoming Events

Share This Page

  • FB SHARE
  • Tweet Page
  • Google+ SHARE

Countdown to Last Day of School!

Quick Links:

Contact Information

Pittsburg ISD
402 Broach St
Pittsburg, Texas 75686
Phone: 903.856.3628
Fax: 903-856-0269

Current Weather

partly-cloudy

Temperature: 59˚F

Current Condition: Partly Cloudy

Wind Speeds: 6.03mph

Chance of Precipitation: 0%

5-day Outlook

Sunday:
partly-cloudy
Temperature: 64/51
Mostly cloudy throughout the day.
Monday:
partly-cloudy
Temperature: 71/49
Mostly cloudy throughout the day.
Tuesday:
partly-cloudy
Temperature: 80/51
Partly cloudy in the morning.
Wednesday:
rain
Temperature: 60/46
Rain starting in the afternoon, continuing until evening.
Thursday:
partly-cloudy
Temperature: 74/48
Partly cloudy starting in the afternoon.